Full access allows:
- Solve all tests online without limits;
- Remove all advertisements on website;
- Adding questions to favorite list;
- Save learning progress;
- Save results of practice exams;
- Watching all wrong answered questions.
A seller and a buyer entered into a written agreement providing that the seller was to deliver 1,000 cases of candy bars to the buyer during the months of May and June. Under the agreement, the buyer was obligated to make a selection by March 1 of the quantities of the various candy bars to be delivered under the contract. The buyer did not make the selection by March 1, and on March 2, the seller notified the buyer that because of the buyer's failure to select, the seller would not deliver the candy bars. The seller had all of the necessary candy bars on hand on March 1 and made no additional sales or purchases on March 1 or March 2. On March 2, after receiving the seller's notice that it would not perform, the buyer notified the seller of its selection and insisted that the seller perform. The seller refused.
There are no comments at the moment. If you found an error or think question is incorrect, tell everyone about it
Only signed in users can write comments
Signin
Pre-UCC, often when parties left open certain terms to be specified by a party at a later date, courts would find no contract existed due to indefiniteness.
A constructive condition is one not agreed on by the parties, but which courts impose as a matter of law, in order to ensure fairness. The distinction between express and constructive conditions is extremely important in relation to performance. Strict compliance with express conditions is ordinarily required. However, constructive conditions will only require substantial compliance to be satisfied. The most common type of constructive condition is when each party's performance is conditioned on the other party's performance. This arises with issues of cooperation or notice, where one party's obligation to perform is impliedly conditioned on the other party's cooperation or notice that the performance is due.
C is correct. The buyer failed to make a selection by March 1 regarding the quantities of the various candy bars to be delivered under the contract, however, the buyer did make the selection on March 2. As of March 2, the seller had all the necessary supplies and made no other transactions by that time, so the fact that the buyer's selection was one day late did not materially alter the seller's performance such that the buyer was in breach. Therefore, the seller's refusal to accept the buyer's selection of goods was not justified and the buyer should recover.
A is incorrect. This answer choice implicates the pre-UCC rule that leaving out a term to be specified by a party later would result in no contract having been formed. However, the UCC rejects this approach and imposes a different set of rules, which allows for leaving open such a term as long as the party's later specification is made in good faith and commercially reasonable. Here, the buyer's failure to specify the needed candy supplies was not fatal to the contract's formation, and it was performed in time so as to not materially alter the seller's performance, as explained above.
B is incorrect. The buyer's duty to select the type and quantity of candy bars was a constructive condition to the seller's ability to deliver those candy bars. The order of these performances necessarily required the cooperation of the buyer to make the appropriate selections so the seller would be able to deliver those selected candy bars.
D is incorrect. This answer reaches the correct answer with the wrong reasoning. The buyer is likely to prevail, but not because of the seller's right to make the selection in lieu of the buyer's selection. That remedy is available under the UCC when the buyer's failure to perform materially affects the seller's ability to perform, which was not the case here, as stated above.