Full access allows:
- Solve all tests online without limits;
- Remove all advertisements on website;
- Adding questions to favorite list;
- Save learning progress;
- Save results of practice exams;
- Watching all wrong answered questions.
A landowner entered into a single contract with a builder to have three different structures built on separate pieces of property owned by the landowner. Each structure was distinct from the other two, and the parties agreed on a specific price for each. After completing the first structure in accordance with the terms of the contract, the builder demanded payment of the specified price for that structure. At the same time, the builder told the landowner that the builder was «tired of the construction business» and would not even begin the other two structures. The landowner refused to pay anything to the builder.
There are no comments at the moment. If you found an error or think question is incorrect, tell everyone about it
Only signed in users can write comments
Signin
When one party performs a single unit under a divisible contract, he is entitled to recover the amount that was agreed upon or the equivalent even if he does not perform the other units or before the entire contract is performed. However, if the partially performing party does not then perform the remaining duties under the contract, he will be subject to liability and the withholding of counter-performance for those units.
A party's basic duty at common law is to substantially perform all that is called for in the contract. This means that a party who substantially complies with a condition of a contract, whether implied or express, can obligate the other party to perform.
D is correct. A divisible contract entitles a party to recover the amount due for a completed unit under that contract, even before completion of the entire contract. This area of contract law acknowledges that parties sometimes combine separate obligations into a single contract. Here, the contract is divisible because it divides performance into three parts, each unique with its own specified structure and price. The landowner contracted to pay three separate prices for three structures to be built by the builder on three tracts of land. It is appropriate for the builder to recover the amount for the first structure as a divisible unit, but the landowner will still be able to recover damages if the builder fails to complete the other two structures.
A is incorrect. The doctrine of substantial performance does not apply here because the builder did substantially perform as to the first structure, which is divisible under the contract. As stated above, the builder will be able to recover for this first completed structure, although the landowner will maintain the ability to recover damages if the builder fails to complete the remainder of the contract.
B is incorrect. The builder's decision to stop performance after completing the first structure does not amount to a willful breach of the contract that would prevent him from recovering for this divisible unit. Although the landowner may seek damages if the builder does not complete the other two structures, this does not negate the builder's recovery regarding the first completed structure. Again, the obligations of the builder were severable for purposes of damages, so the landowner will not preclude the builder from recovering as to the first structure based on his choice not to complete the other two.
C is incorrect. This answer is only partially correct. The contract is divisible, for the reasons provided above, but the landowner will not be required to bring a separate claim regarding the other two structures. Even when a contract is divisible, the resolution of the remainder of the contract duties does not necessitate separate causes of action. If an injured party were required to bring separate actions, this would be inconsistent with the legal system's goal of efficient disposition, in a single action, of closely-related claims. As such, the builder is likely to recover the agreed price of the first structure, less any recoverable damages caused to the landowner in the event of the builder's breach.