On the first day, the arborist cut down all the trees. That evening, a fire caused by vandals completely destroyed the trees, making them unfit for use by the lumber company.
A property owner hired an arborist to cut down all the trees on her property and to transport the trees to a lumber company. The owner agreed to pay the arborist $10,000 when the work was complete. The arborist said that the work would take him three days.
There are no comments at the moment. If you found an error or think question is incorrect, tell everyone about it
Only signed in users can write comments
Signin
A is incorrect. Expectation damages are a remedy for breach of contract, and here the owner is not in breach. Rather, the arborist was unable to complete performance due to impracticability.
C is incorrect. The arborist is entitled to restitutionary relief, whether the parties' performance was excused by impracticability or frustration of purpose.
D is incorrect. The arborist's failure to complete the work was excused by impracticability and he is entitled to recover in restitution for the benefit conferred.